An office fit-out in Ireland typically takes 6-14 weeks, depending on its size and complexity. As a guide to how long an office fitout takes, allow around 6-10 weeks for Category A and 10-14 weeks for Category B. The construction period is only part of the schedule.
It’s natural to focus on when the space will be ready: a move affects staff, daily operations and planning. The timeline also depends on what the office needs before work begins, including design decisions, approvals, and ordering materials and furniture.
This guide explains how Category A and Category B timelines differ, what construction and installation involve, and which factors can extend or streamline the schedule. You’ll get a clearer picture of how the stages fit together and what to consider when planning a move-in date.
Key Takeaways
- Compare the scope of Category A and Category B work to understand which type of fit-out your office needs.
- Separate the on-site construction period from the full project timeline, which also includes design, approvals and procurement.
- Identify items with longer procurement lead times early, as they can affect when installation is complete.
- Factor in the condition of the space and the complexity of the specification when planning your intended move-in date.
Category A and Category B fit-out durations
Category A work prepares the office with core finishes and building services, while Category B shapes it for a particular business. As a guide, Category A takes around 6-10 weeks; Category B often takes 10-14 weeks. The extra time commonly reflects the detailed layout, finishes and facilities needed for staff.
Project size and specification make a material difference. A straightforward Category B fit-out for a 3,000-5,000-square-foot office may take 8-10 weeks. A bespoke project in a space of 10,000 square feet or more can take 12-14 weeks or longer. Larger or more bespoke office fit-outs can take up to 6 months overall.
- Warm shell: Count back at least 20 weeks from the intended occupation date.
- Bare shell: Count back at least 26 weeks, allowing more time for the work required to create a usable office.
Those planning windows help explain why construction dates alone don’t answer how long an office fit-out takes. The overall programme also includes design, approvals and procurement, which can overlap with one another. Design development may take 4-8 weeks, while furniture review and ordering can also take 4-8 weeks.
For a realistic move-in plan, first identify whether the space is a warm shell or bare shell, then define the Category A or B scope. A detailed specification, bespoke finishes and a larger footprint can extend the programme. A simpler layout and a space ready for fit-out may require less work. Treat the intended occupation date as the deadline for the whole project, not just construction.
Construction and installation
Construction on an office fit-out typically takes 6-14 weeks, depending on the project’s size and complexity. Site preparation and health-and-safety works may take 1-2 weeks before the main build. The sequence then moves through construction, installation and final checks, with the work shaped by the agreed specification.
Ordering and delivering furniture and materials takes different amounts of time. Furniture orders and bespoke workstation procurement can affect the project timeline. Glass partitions can take 4-8 weeks, and imported flooring or specialist lighting may take 6-12 weeks. These lead times can overlap with site work if selections and orders are made early.
Installation is a distinct stage. Furniture installation is estimated at 1 week, but it follows delivery and depends on the space being ready. A practical sequence is to complete building work first, then install furniture and equipment, followed by testing, snagging and handover. Coordinating deliveries with site access helps avoid materials arriving before areas can receive them.
Allow time for final checks as well as visible construction. Smaller offices may be signed off within a week, while the scope of testing and commissioning depends on the systems installed. For example, new services need to be checked before the space is ready for occupation. The move-in date should follow installation and handover, not simply the last day of building work.
Careful coordination of design, procurement and site delivery can make the programme easier to manage. Explore office fit-out planning as part of shaping a workspace around its practical requirements.

Factors affecting project timelines
Lease negotiations can take 8-12 weeks, delaying access before fit-out work begins. Selecting and appointing a contractor can affect the project timeline. These stages can overlap, but unresolved decisions may push back the start date. A clear brief helps define the scope before design and procurement progress.
For a Category B project, allow at least 4-6 weeks before construction for design development, landlord approvals and long-lead procurement. Approvals and compliance can take 2-4 weeks in a traditional fit-out. Complex projects may require several weeks to several months for licences and approvals, depending on project complexity and local authority timescales.
Procurement is another common source of delay. Custom-finished workstations may take 6-10 weeks, while imported flooring and specialist lighting may take 6-12 weeks. Late choices can leave less time for delivery before installation. Confirming the specification early helps coordinate orders with the construction programme.
Businesses can protect quality and compliance by agreeing the scope early, resolving design decisions promptly and ordering long-lead items before site work begins. A single design-and-build contract typically saves three to five weeks on a mid-sized office fit-out. Keep approvals, testing and final checks in the programme rather than cutting them short to recover lost time.
To reduce avoidable delays, set decision dates for the brief, finishes and furniture, then track approvals and deliveries against the schedule. Plan your office fit-out around the design, procurement and construction stages.
Jas Interiors: Build to Rent Accommodation Fitouts
Jas Interiors delivers Build to Rent Accommodation Fitouts, creating functional, high-quality interiors tailored to each development’s needs. If your project is accommodation rather than an office, this is the relevant next step: fit-out planning must reflect the intended use and the experience residents need from the space.
Jas Interiors also provides Student Accommodation Fitouts, Hotel Fitouts Design and Residential Interior Design. These services suit accommodation and hospitality projects rather than office fit-outs. Defining the project type and its practical requirements helps set the right design direction and scope of work.
For an accommodation or interior design project, contact Jas Interiors to discuss your plans.
Set your office fit-out in motion
Knowing how long an office fit-out takes is most useful when it helps you set a workable business milestone, not just a target handover date. Bring together the people who will use the space and agree what they need to do their day-to-day work. Clear priorities give design decisions a purpose and help the finished workplace reflect how your organisation operates.
A considered brief also gives everyone involved a shared basis for weighing layout, collaboration, privacy and how teams work. Jas Interiors’ Office Fitouts and Design can translate those priorities into a tailored workspace. Start a focused conversation about your project and the environment you want to create.
Discuss your fit-out with Jas Interiors, and take the next step towards a workplace shaped around your needs.
Frequently Asked Questions
What is an Office Fit Out?
An office fit-out turns a commercial interior into a workspace suited to a business’s needs. It can involve space planning, selecting suitable furniture and lighting, integrating branding and coordinating installation. For example, an open-plan office may need defined meeting areas and workstations, while a client-facing space may call for a distinct reception area. The scope depends on how the workplace will be used.
How long does a typical office fit-out take in Ireland?
A typical office fit-out takes 6-14 weeks, with the category and project scope shaping the programme. Category A projects commonly take around 6-10 weeks, while Category B projects often take 10-14 weeks. These estimates describe typical durations, not a guaranteed handover date. A bespoke specification or larger office may need a longer overall programme.
How long do office fit-out construction and installation stages take?
Construction typically takes 6-14 weeks, while furniture installation is estimated at 1 week. These stages need to be planned around the work sequence: the space must be ready for furniture before installation can proceed. Final checks, including snagging and commissioning, also form part of preparing the office for occupation.
What factors can delay an office fit-out project?
Late design decisions, approvals and procurement can all affect the schedule. For example, changing workstation finishes may affect an order already in progress, while landlord approvals can delay work before construction starts. Agreeing the scope and key selections early helps the project team coordinate decisions, deliveries and site activities with fewer avoidable interruptions.
What is the typical office fit-out project timeline from lease signing to move-in?
After lease signing, the programme usually moves through briefing and design, approvals, procurement, construction, installation and handover. For a Category B fit-out, allow at least 4-6 weeks before construction for design development, landlord approvals and long-lead procurement. Some stages can overlap, so the overall schedule depends on the space, decisions and delivery coordination.